If you're planning to build a house in Nigeria but unsure about the true costs involved, this article helps you understand current construction expenses and budget effectively.

This  article breaks down the real costs you'll face — and shows you how to avoid budget overruns that destroy construction projects.

 

How Much Does It Cost to Build a House in Nigeria 2025: Complete Breakdown for Lagos and Abuja (Materials, Labor & Permits)

Published: July 19, 2025

Written by Abdulateef Muhammed

Author of Nigerian Lawyer's Playbook

Founder: ASM Real Estate Solicitors

INTRODUCTION

Building your house in Nigeria has become increasingly expensive, with construction costs rising significantly due to inflation, currency fluctuations, and supply chain challenges.

Whether you're planning to build in Lagos or Abuja, understanding the complete cost breakdown is essential for proper budgeting and project planning. This comprehensive guide provides current 2025 pricing for materials, labor, permits, and all associated costs to help you build your dream home without financial surprises.

 

CURRENT CONSTRUCTION MARKET REALITY IN NIGERIA 2025

The Nigerian construction industry faces unprecedented challenges in 2025. Inflation continues to be a significant concern, influencing the prices of cement, steel, roofing sheets, and finishing materials.

Additionally, government policies and import tariffs continue to contribute to sudden price spikes across all construction materials.

 The cost differential between Lagos and Abuja remains substantial. A 9-inch building block can go for 120 per piece in places like Ekiti and Yola, yet the same product would sell for as much as 180 or even 200 per piece in places like Lagos and Abuja.

 

 

 🧠 QUICK TIP

Location = Cost Multiplier

Construction costs in Lagos and Abuja are typically 40-60% higher than other Nigerian cities. Factor this premium into your budget from day one.

 

 

Understanding these market dynamics is crucial for accurate budgeting. Many construction projects fail not due to poor planning, but because owners underestimate the true cost of building in Nigeria's major cities.

 

YOUR COMPLETE COST BREAKDOWN BY HOUSE TYPE

 

 Standard 3-Bedroom Bungalow

 

Lagos Costs:

Total Construction Cost: 25-35 million

Cost per square meter: 65,000-85,000

 Typical floor area: 120-150 sqm

 

Abuja Costs:

 Total Construction Cost: 22-30 million

Cost per square meter: 60,000-75,000

Typical floor area: 120-150 sqm

 

What's Included:

Foundation and structural work

Roofing and electrical installation

Basic plumbing and tiling

Standard doors and windows

Basic finishing materials

 

 

 📌 CASE HIGHLIGHT

The Hidden 30% Rule

A Lagos homeowner budgeted 28M for a 3-bedroom bungalow but spent 36M. The extras: soil testing (200K), additional permits (800K), design changes (2.5M), and material price increases during construction (4.5M).

 

 

 4-Bedroom Duplex (Standard)

 

Lagos Costs:

Total Construction Cost: 45-65 million

Cost per square meter: 70,000-90,000

Typical floor area: 200-250 sqm

 

Abuja Costs:

Total Construction Cost: 40-55 million

Cost per square meter: 65,000-80,000

Typical floor area: 200-250 sqm

 

Luxury 5-Bedroom Duplex

 

Lagos Costs:

Total Construction Cost: 80-120 million

Cost per square meter: 90,000-130,000

Typical floor area: 300-400 sqm

 

Abuja Costs:

Total Construction Cost: 70-100 million

Cost per square meter: 85,000-115,000

Typical floor area: 300-400 sqm

 

 

 ⚖️ LEGAL NOTE

Contract Price vs Final Cost

Nigerian law requires builders to honor quoted prices, but most contracts include escalation clauses for materials. Review these clauses carefully before signing any construction agreement.

 

 

 CURRENT MATERIAL COSTS: WHAT YOU'LL ACTUALLY PAY

 

Foundation Materials (2025 Prices)

 

Cement:

Lagos: 5,200-5,800 per 50kg bag

 Abuja: 4,800-5,400 per 50kg bag

 Your requirement: 200-300 bags for standard 3-bedroom

 

Sand and Granite:

Lagos: 35,000-45,000 per tipper load

 Abuja: 30,000-38,000 per tipper load

Your requirement: 15-20 tipper loads for standard foundation

 

Building Blocks:

Lagos: 180-220 per 9-inch block

Abuja: 150-180 per 9-inch block

Your requirement: 2,000-3,500 blocks for standard 3-bedroom

 

 

 🚩 COMMON MISTAKE

Buying Materials Too Early

Many builders purchase all materials upfront to "lock in prices." But cement and steel deteriorate in storage, often costing more than price increases would have.

 

 

Roofing Materials

 

Aluminum Roofing Sheets:

Lagos: 3,800-4,200 per sheet

Abuja: 3,500-3,900 per sheet

Coverage: Each sheet covers approximately 1.8 sqm

 

Steel Roofing (Long Span):

Lagos: 4,500-5,200 per sheet

Abuja: 4,200-4,800 per sheet

 

Roofing Timber:

Lagos: 180,000-220,000 per cubic meter

Abuja: 160,000-200,000 per cubic meter

 

Electrical and Plumbing

 

Electrical Materials (Complete House):

Basic 3-bedroom: 800,000-1,200,000

4-bedroom duplex: 1,500,000-2,200,000

Luxury 5-bedroom: 2,500,000-4,000,000

 

Plumbing Materials:

Basic 3-bedroom: 600,000-900,000

 4-bedroom duplex: 1,200,000-1,800,000

Luxury 5-bedroom: 2,000,000-3,500,000

 

 Labor Costs: What Skilled Workers Charge

 

 Skilled Labor Rates (2025)

 

Mason (Daily Rate):

Lagos: 8,000-12,000

Abuja: 7,000-10,000

 

Carpenter (Daily Rate):

Lagos: 7,500-11,000

Abuja: 6,500-9,500

 

Electrician (Daily Rate):

Lagos: 10,000-15,000

Abuja: 8,500-13,000

 

Plumber (Daily Rate):

Lagos: 9,000-14,000

Abuja: 8,000-12,000

 

 

 📌 CASE HIGHLIGHT

The Specialist Premium

A homeowner in Lagos needed specialized tiling work. Regular tilers quoted 8,000/day, but the specialist charged 18,000/day. The result? Perfect installation that added 2M to property value.

 

 

 Labor Cost by Construction Phase

 

Foundation Work (3-bedroom):

Lagos: 3,500,000-4,500,000

Abuja: 3,000,000-3,800,000

 

Roofing Work:

Lagos: 2,200,000-2,800,000

 Abuja: 1,900,000-2,400,000

 

Finishing Work:

Lagos: 4,500,000-6,500,000

Abuja: 3,800,000-5,500,000

 

 Permit Costs and Government Approvals

 

 Lagos State Building Permits

 

Building Plan Approval:

3-bedroom bungalow: 180,000-250,000

4-bedroom duplex: 320,000-450,000

5-bedroom luxury: 500,000-750,000

 

Development Permit:

Standard residential: 150,000-300,000

 Luxury residential: 400,000-600,000

 

Environmental Impact Assessment (if required):

Basic assessment: 500,000-800,000

Comprehensive assessment: 1,200,000-2,000,000

 

 

 ⚖️ LEGAL NOTE

Permit Timeline Reality

Lagos building permits typically take 60-90 days if you submit complete documentation. Missing documents can extend this to 6-12 months. Fines for non-compliance with building permit regulations can range from 50,000 to 1 million.

 

 

 Abuja (FCT) Building Permits

 

Building Plan Approval:

3-bedroom bungalow: 150,000-200,000

4-bedroom duplex: 280,000-380,000

5-bedroom luxury: 450,000-650,000

 

Development Control Approval:

 Standard residential: 120,000-250,000

Luxury residential: 350,000-500,000

 

 Additional Permit Costs

 

Utility Connections:

Electricity connection: 150,000-300,000

Water connection: 80,000-150,000

 

Professional Fees:

Architect fees: 3-5% of total construction cost

Structural engineer: 1-2% of construction cost

Building approval consultant: 200,000-500,000

 

 

 🧠 QUICK TIP

The Professional Fee Investment

Hiring qualified professionals upfront costs 5-7% of your budget but can save 15-25% by preventing mistakes, design changes, and permit delays.

 

 

Hidden Costs That Destroy Budgets

 

 Site Preparation Costs

 

Land Clearing and Leveling:

 Lagos: 300,000-600,000

Abuja: 250,000-500,000

 

Soil Testing and Geotechnical Survey:

Basic soil test: 150,000-250,000

Comprehensive geotechnical survey: 400,000-800,000

 

Site Security and Fencing:

 Temporary fencing: 200,000-900,000

Security services (6-month project): 300,000-600,000

 

Access and Infrastructure

 

Road Access (if required):

Basic access road: 500,000-1,500,000

Drainage and culverts: 300,000-800,000

 

Generator and Power Solutions:

Site generator rental: ₦150,000-180,000 per month

Fuel costs: 100,000-150,000 per month

 

 

 🚩 COMMON MISTAKE

Underestimating Site Costs

Many builders focus only on materials and labor, forgetting site preparation can add 10-20% to total project cost, especially in undeveloped areas.

 

 

Design Changes and Variations

 

Mid-Construction Changes:

Minor modifications: 5-10% cost increase

Major design changes: 15-30% cost increase

Structural modifications: 25-50% cost increase

 

Material Upgrades:

Standard to premium tiles: 1,000,000-3,000,000 additional

Basic to luxury fixtures: 2,000,000-5,000,000 additional

Standard to imported materials: 40-80% price premium

 

 Your Monthly Budget Planning Guide

 

3-Bedroom Bungalow Construction Timeline

 

Month 1-2: Site Preparation and Foundation

Lagos budget required: 8,000,000-12,000,000

Abuja budget required: 7,000,000-10,000,000

 

Month 3-4: Block Work and Roofing

Lagos budget required: 10,000,000-14,000,000

Abuja budget required: 8,500,000-12,000,000

 

Month 5-6: Finishing and Utilities

Lagos budget required: 7,000,000-10,000,000

Abuja budget required: 6,000,000-8,500,000

 

 

 📌 CASE HIGHLIGHT

The Cash Flow Crisis

A builder in Abuja had 30M total budget but poor cash flow planning. Work stopped in month 4 when materials suppliers demanded payment, extending the project by 8 months and adding 4.5M in additional costs.

 

 

 SMART BUDGETING STRATEGIES

 

The 20% Contingency Rule

Always add 20% to your total estimated cost for unforeseen expenses. In Nigeria's volatile construction market, this contingency often proves insufficient.

 

 Phased Payment Strategy

 10% advance to contractor

 25% on foundation completion

 30% on roofing completion

 25% on electrical and plumbing completion

10% final payment on project completion

 

Material Purchase Timing

Buy non-perishable materials (tiles, fixtures) early if prices are rising

 Purchase cement and steel just-in-time to avoid deterioration

Secure imported materials early due to longer lead times

 

COST-SAVING STRATEGIES THAT ACTUALLY WORK

 

 Material Sourcing Strategies

 

Direct Factory Purchases:

Cement: Save 8-15% buying directly from manufacturers

Roofing sheets: 10-18% savings from factory purchases

Tiles and fixtures: 15-25% savings from wholesalers

 

Group Buying with Other Builders:

Organize purchases with neighbors or other builders

Typical savings: 5-12% on bulk materials

Best for: cement, sand, granite, and roofing materials

 

 

 🧠 QUICK TIP

The Rainy Season Advantage

Material prices often drop 5-10% during rainy season when construction activity slows. Plan your material purchases accordingly.

 

 

LABOR COST MANAGEMENT

 

Skilled Team Assembly:

 Hire teams that work well together

Reward quality work with bonuses

Provide comfortable site conditions

 

Task-Based vs Daily Rate Contracts:

Block laying: 80-120 per block (often more efficient than daily rates)

Plastering: 800-1,200 per square meter

Tiling: 1,500-2,500 per square meter

 

TECHNOLOGY AND MODERN CONSTRUCTION METHODS

 

 Prefabricated Components

 

Precast Concrete Elements:

Cost: 15-20% premium over traditional methods

Benefits: Faster construction, better quality control

Time savings: 20-30% reduction in construction time

 

Steel Frame Construction:

Cost: 25-35% premium for materials

Benefits: Earthquake resistance, faster assembly

Best for: Multi-story buildings and areas with soil challenges

 

Smart Building Integration

 

Basic Smart Home Features:

Smart electrical system: 800,000-1,500,000

Security integration: 600,000-1,200,000

Automated lighting: 400,000-800,000

 

Energy Efficiency Upgrades:

Solar power system: 2,500,000-5,000,000

Energy-efficient windows: 40-60% premium over standard

Insulation systems: 300,000-600,000 additional

 

 

 ⚖️ LEGAL NOTE

Technology Contract Clauses

Smart home and solar installations often require separate contracts with specialized warranties. Ensure these are properly structured to avoid disputes.

 

 

 FINANCING YOUR CONSTRUCTION PROJECT

 

Construction Loan Options

 

Commercial Bank Construction Loans:

 Interest rates: 18-25% per annum

Loan-to-cost ratio: 70-80%

 Typical tenor: 12-24 months

 

Mortgage Construction Financing:

 Interest rates: 15-22% per annum

Down payment required: 20-30%

Converts to mortgage upon completion

 

Developer Financing:

Down payment: 30-50%

Interest rates: 12-18% per annum

Often includes land purchase

 

Alternative Financing Methods

 

Cooperative and Contribution Systems:

Popular in Nigerian communities

 Lower interest costs but requires group management

Timeline flexibility often better than bank loans

 

Family and Personal Financing:

Often the most flexible option

Consider formal agreements to avoid disputes

Document all contributions and expectations

 

 

 📌 CASE HIGHLIGHT

The Family Investment Strategy

A Lagos professional raised 40M for construction through family members, offering 12% annual returns. The house was completed 3 months early and family members received both returns and increased property value.

 

 QUALITY CONTROL AND AVOIDING CONSTRUCTION FRAUD

 

Material Quality Verification

 

Cement Testing:

 Always test cement strength before use

Cost of testing: 15,000-25,000 per batch

Fake cement can cost 300% more in remedial work

 

Steel Bar Verification:

Check for proper manufacturer marking

Test tensile strength for structural elements

Quality steel prevents future structural failures

 

Contractor Verification Process

 

Essential Checks Before Hiring:

Verify previous project completions

Check professional certifications

Obtain and verify references from recent clients

Review insurance and bonding status

 

Red Flags to Avoid:**

📌  Requests for large upfront payments (>15%)

📌  No fixed address or proper business registration

📌  Extremely low bids compared to others

📌  Pressure for immediate signing without review time

 

 

🚩 COMMON MISTAKE

Choosing Based on Price Alone

The cheapest contractor often becomes the most expensive. Quality contractors charge 10-15% more but deliver projects on time and budget.

 

 

 FUTURE-PROOFING YOUR INVESTMENT

 

 Market Value Considerations

 

Features That Add Long-Term Value:

Quality electrical installations supporting modern appliances

 Proper waterproofing and drainage systems

 Energy-efficient systems and solar readiness

 Security system pre-wiring and integration

 

Location-Specific Additions:

 Lagos: Flood-resistant features, backup power systems

Abuja: Solar systems, water storage, security fencing

 

 Maintenance Budget Planning

 

Annual Maintenance Costs:

 Basic maintenance: 1-2% of construction cost annually

 Major repairs (5-year cycle): 3-5% of construction cost

 Utilities and security: 200,000-500,000 annually

 

 MAKING YOUR CONSTRUCTION DECISION

Building your house in Nigeria requires substantial capital, careful planning, and realistic budgeting. With construction costs ranging from 25-35 million for a basic 3-bedroom bungalow to 80-120 million for luxury 5-bedroom duplexes in Lagos and Abuja, proper financial planning is essential.

The key to successful construction lies in understanding that quoted prices are starting points, not final costs. Budget for a 20% contingency, plan your cash flow carefully, and invest in quality professionals and materials.

While construction costs continue to rise, property values in Lagos and Abuja have historically grown faster than construction costs, making building a sound long-term investment.

Your success depends on choosing the right professionals, understanding true market costs, and maintaining realistic expectations about timelines and budgets.

With proper planning and the information in this guide, you can build your dream home while avoiding the financial pitfalls that trap many Nigerian builders.

 

DISCLAIMER: Construction costs vary significantly based on specific requirements, market conditions, and contractor selection. This guide provides general cost estimates based on current market data. Obtain detailed quotes from qualified professionals for your specific project. Consult with legal professionals before signing construction contracts or making significant payments.

 

ABOUT THE WRITER

Abdulateef Muhammed is the founder of ASM Real Estate Solicitors. He earned his law degree from the University of Lagos in 1997 and was called to the Nigerian Bar in 1998. In 2018, he was appointed a Notary Public for life by the Chief Justice of Nigeria.

From 2022 to 2024, he served as the Vice Chairman of the Nigerian Bar Association, Kabba Branch.

He is the author of several legal and creative works, including:

A Nigerian Lawyer’s Playbook: What Law School Doesn’t Teach About Litigation Practice

Three Short Nigerian Plays (For Simple Staging and Strong Performances)

Foot Rub and Coffee Black ( two full length screenplays published as part of the Nollywood Screenplay Library Series)

His legal writing focuses on uncovering the hidden patterns behind litigation and exploring strategic aspects of legal leverage in Nigeria.

This article is part of ListedByOwners and ASM Real Estate Solicitors’ FREE educational  series, helping Nigerian property buyers and sellers navigate fraud-free transactions.

For professional property listing and verification services backed by legal oversight contact ASM Real Estate Solicitors via the link below or directly via WhatsApp chat.